What are the installation methods of DP Current Transformer?
The installation method of DP Current Transformer depends on the transformer structure and application scenario. There are two main types: closed and open. Specific differences and applicable scenarios are as follows:
1.Closed-type Installation (Traditional Hole-Through Installation)
Structural features:
The transformer is designed with a closed loop and the main conductor must pass through the central hole of the transformer.
Installation Steps:
Power Outage Operation: Disconnect the power supply to the circuit being tested to ensure safety.
Conductor insertion: passes through the central hole of a transformer through the main conductor,such as a bus or cable.
Fixed the Transformer: Bolt or brace transformer to mounting panel or track.
Secondary wiring: Connect the secondary wiring to the measuring instrument or protective device to ensure correct polarity (inside K1, outside K2).
Applicable Scenarios:
New project: Reservation of installation space during the design phase of switchgear and distribution boxes.
Closed environment: For example, the interior of a high-voltage switchgear needs to be protected from external interference.
High precision measurement: closed structure, reduce electromagnetic leakage, suitable for energy metering. Note:
Installation requires a power outage, which affects system's uptime.
The cross-sectional product of the conductor must match the central hole of the instrument transformer (for example, a DP-23 conductor can hold 10mm2 to 50mm2).
Avoid mechanical stress, so as to avoid instrument transformer deformation during installation.

2. Split-Type Installation (Split/Clamp-Type)
Structural features:
The instrument transformer consists of two upper and lower halves that can be quickly opened and closed with switches or bolts without breaking the original conductor.
Installation Steps:
Turn instrument transformer on: Separate upper and lower half, exposing central hole.
Clamp conductor: Wrap the instrument transformer around the original conductor and close, ensuring tight contact.
Lock device: fastened with bolts or clamps to prevent loosening.
Secondary wiring: connecting secondary wires, such as closed mounting.
Applicable Scenarios:
System modifications during operation: such as adding monitoring points or replacing faulty instrument transformers without power outage.
Interim measures: for rapid deployment of energy efficiency management systems or fault diagnosis equipment.
Space-restricted situations: for example, on narrow cable trenches or densely packed busbars. Typical Model:
DP-58: Supports 3000A/5A split-type installation for medium-voltage systems;
DP-23L: Lightweight design for rapid expansion of low-voltage distribution cabinets.
Preventive measures:
In long-term operation, it is necessary to inspect the sealed position regularly to prevent heat from being generated by poor contact.
Avoid use in high vibration environments (such as nearby wind turbines) as this can cause loosening;
When selecting a model, confirm that the opening size matches the conductor diameter (e.g., the opening diameter of DP-58 ≤ 120mm).
3. Special Installation Methods (Custom)
Structural features:
Customizable mounting structures, such as flat panel, busbar, or embedded DP transformer.
Examples of applications:
Busbar Direct Mounting: transformer embedded a busbar fixture, reduce space usage;
Track installation: adjustment of installation position by sliding track, suitable for modular distribution system;
Explosion proof installation: In the chemical, oil and gas industries, use of sealed structures to meet explosion proof requirements (e.g., Ex d IIC T4 certification). Selection Recommendations:
For custom installation, discuss conductor specifications, environmental conditions (such as temperature and vibration) and certification requirements with the manufacturer in advance.